The fact that even the "first coat" of the backdrop painting stops here is a clue that the Stafford Mills area of the layout is unresolved. |
In this case I didn't have to remove anything so this wasn't so much a "rework" as it was an addition or an enhancement. I could even make the argument this didn't add any additional track to the layout since I'd removed a turnout and a siding from the junction area as part of the rework of that trackage I described a few months ago.
I was out of Micro Engineering no. 6 code 70 turnouts - as is everyone else. So I decided to handlay the necessary turnout. Although this added a couple of evenings to the project I'm glad I did - the turnout works perfectly, and cars and locomotives (even brass steam locomotives!) pass through both routes without so much as a click! I'm not wishing any additional work on myself, but if any of the Micro Engineering turnouts on the rest of the railroad fail or prove troublesome I'm simply going to replace them with handlaid ones.
The buildings shown in the photos are strictly placeholders and may, or may not, end up in these locations permanently. I kind of like the idea of a station in between the mill lead and mainline, so that will likely stay (I may build a different station for the spot. The one shown is a model of the Richmond, Vermont station - although that perhaps the closest to a "standard" CV small depot design as the railroad had. But there are a couple of Grand Trunk (NEL) stations I've always liked and may well scratchbuild one of those for this spot.
The freighthouse is a Walthers cheapo model that I painted and lettered in "close enough" CV colors. It's not bad .... but the weakest point is the platform - despite my best efforts it's still too bulky. I should have replaced it with a scratchbuilt wood one. I do have a BEST Trains kit that may work better in this spot, if I decide to stick with the freight house.
The red rectangular building is simply there to fill space and see how a larger industry would look in that spot. I'm not convinced it's going to work there - especially with the freight house. The answer is looking like (1) freight house and something that isn't a large building - a coal yard for example or team track OR (2) a larger building industry with no freight house. Since there's going to be plenty of large buildings in the mill complex I'm leaning towards option #1.
My ultimate plan for the area with inside the mainline curve (with the yellow building) is to ultimately have a mill river with one or two larger wooden mill structures over a mill stream, complete with mill falls, etc. ... But that sounds like it may take months/years to get completed. This may well simply end up as some open fields and a tree line "for now" to get a large portion of the landscape to look finished with the idea I could revisit it at some future point.
Have you changed the trackwork (The branch from the main) into Sheldon Jct/Stafford Mills?
ReplyDeleteNo changes.
ReplyDeleteWhen I laid out the benchwork I saw I had room to angle the track from the wall, so that's what I did. The original track plan had the track running parallel to the wall on the left in these photos.
Marty